From site survey to switch-on in ten days

What happens on each of the ten days, who turns up, and the two approvals that decide whether the schedule holds.

SK Sandeep Kaul Field operations · 07 Jul 2026
Installation crew mounting solar modules
Mounting day. Structure first, modules second, electrical third — in that order, every time.

On this page

Days one to three: survey and design Days four to seven: fabrication and paperwork Days eight to ten: install and commission

Reading time

5 min read

Ten days is the schedule we quote and the schedule we hit on most residential jobs. It is worth seeing where those days actually go, because only three of them involve anyone on your roof.

Days one to three: survey and design

A surveyor measures usable roof area, checks shading through the day, inspects the existing structure and photographs the meter and distribution board. That visit produces the single-line diagram, the structure drawing and the final bill of materials. Approvals go in the same day.

Days four to seven: fabrication and paperwork

Structure is fabricated to the roof's dimensions while the net-metering application sits with the discom and the subsidy packet is registered. Nothing happens on site during this window, which is the part customers find hardest and the part we cannot compress.

Days eight to ten: install and commission

Day eight: structure goes up and is anchored. No modules yet.
Day nine: modules mounted and strung, inverter and safety gear installed, earthing completed.
Day ten: commissioning tests, monitoring paired to the app, handover with the asset passport.

The one thing that can move the date

Net-meter sanction sits with the discom. When it runs long, the system still generates for self-consumption from day ten — you simply cannot export until the meter is swapped.

What to take away

Physical work takes two to three days; the rest of the calendar is approvals and fabrication.
The survey decides the design, so an hour spent on the roof saves a week later.
Net-meter sanction is the one milestone outside our control — start it on day one.
Installation Process Timeline
SK

Sandeep Kaul

Field operations

Runs survey and installation crews. Fifteen years on North Indian roofs, most of them in the two weeks before monsoon.

Run these numbers against your own bill

The calculator uses state-wise generation data and the current subsidy slabs. Two inputs, one estimate, no call required.

Open calculator Talk to us

Keep reading

All articles
Solar 101
What 3 kW really powers in a Delhi home Aditya Pandey · 4 min read
Panels
Mono PERC, TOPCon, bifacial: choosing without the jargon Meera Iyer · 8 min read
Storage
Charging by day to run the night Meera Iyer · 6 min read
RePrime

Clean energy, delivered end to end — from the first savings estimate to live generation on your roof.

MNRE empanelled ALMM listed ISO 9001

Solutions

Residential Commercial Housing societies Industrial Data centres Procurement Roof assessment

Plans & pricing

Plans & pricing

Products

Solar panels Battery storage RePrime app EV charging Smart meters ReLink Intelligence Ecosystem

Meet RePrime

Why RePrime Our guarantee Solar by state Customer stories Equipment for installers Refer and earn Careers

Need help?

Contact us Learn center Why solar Moving made easy FAQs RePrime blog

© 2026 RePrime Energy. All rights reserved.

Additional pages
Calculator Light Component Library Financing Icons 3D Hero Margin A Hero Margin B Hero Margin C Hero Mobile C Landing Plans Section On-Grid Solar Preserved components (archive) Purchase Solar Panels copy Residential Mobile C Residential Solutions Heroes Solution
Terms Privacy policy Manage cookies Editorial guidelines MNRE empanelment